Info on the East Riverside Energy Center

In August, NextEra Energy hosted an open house at Brownsville High School to announce their plans for the East Riverside Energy Center, a 700+ acre, 3.75GW power plant in Fayette County’s Luzerne Township, right along the Monongahela River. Since then, public information on the project has been sparse, but the development is still quietly moving forward.

Even though MWA is not aware of any permit documents filed with PA DEP, the company appears to have been drilling core samples to assess ground stability, approaching nearby landowners for “participation agreements,” and communicating with local leaders to develop an agreement for the project. 

Some of the area which would be affected by the plant, according to NextEra’s materials

Why is the company drilling?

In the past few months, residents have reported heavy equipment coming and going from the site, reddish sheens in puddles along the road consistent with dyed off-road diesel which is commonly used for construction equipment, as well as more frequent patrolling from law enforcement. Drilling might be to help evaluate the ground’s stability, which can inform the plant’s design, or whether or not the site is suitable for such a large development in the first place. The company has not publicly stated the purpose of the work. 

What appears to be foreign fluid was documented in puddles and ditches near East Riverside Road.

Representatives of NextEra and Fayette County have advertised the site as ideal due to its history of strip mining, but some of the locals say the area has since been fully reclaimed and used for agricultural purposes. Little has been discussed about the extensive abandoned underground mines just beneath the site, though. 

Between the 1900s and the 1950s, the Filbert and Palmer mines cleared out the Pittsburgh coal seam in much of Luzerne, German, and Redstone Townships. With such a large mine void beneath the site, community members have expressed concerns about mine subsidence possibly damaging the proposed power plant. If the power plant is built above a mine void which could fracture or collapse under the added weight of a giant power plant, cooling towers, turbines, pipelines and more could potentially be damaged.

Just some of the mining that has taken place under the proposed site

What are Participation Agreements?

Several community members who live closeby to the development have reached out to MWA to ask questions about participation agreements sent to them by NextEra. These agreements ask property owners to waive several rights for a simple cash payment. 

The rights property owners are asked to give up include a right to setbacks as defined by the Fayette County Zoning Ordinance and other government authorities, the right to comment, file complaints, protest, and appeal any part of the operation, and the right to sue if they are to face impacts. If you receive one of these agreements, it is important to consult with a lawyer. 

Next Steps

Mountain Watershed and Center for Coalfield Justice are partnering to host an informational community meeting on December 1st, 6:00PM at 173 East Riverside Road in Adah,  PA. For those interested in attending virtually, register here. For those joining in person, food and beverages will be provided.